PMI-ACP Preparation Exam Mocktest2 - Whizlabs

Question 92 of 120
Sam is working as a Scrum master and he is doing planning activities along with the team. They are using historical approach to estimate the velocity for upcoming sprint. They have completed 5 sprints so far with the velocities of 9, 12, 14, 10 and 15. What will be the estimated velocity for next sprint?