PMI-ACP Preparation Exam Mocktest2 - Whizlabs

Question 73 of 120
Till the completion of the third sprint, a scrum team has completed ΒΌ of the story points needed for the completion of the whole project with an average velocity of 20 story points per sprint. As per the estimation of the team, the average cost for achieving a story point is $500. What will be the expected cost of developing the left part of the project.