PMI-ACP Preparation Exam Mocktest2 - Whizlabs

Question 71 of 120
Some of the agile project stakeholders are inspecting the number of story points completed by the team in each iteration and putting the extra pressure on the team to enhance the performance. In the next iteration, some extra steps were taken by the team that resulted in increased velocity although no extra work was done by the team than the planned one. Out of the following, what could be the most likely step taken by the team?