PMI-ACP Preparation Exam Mocktest2 - Whizlabs

Question 69 of 120
A software development project has been assigned to an agile team. While working to determine the ideal iteration length, two members of the team have an intense and long argument on it. While one member advocates for two weeks iteration length, other advocates for three weeks iteration length. What should the scrum master do in this situation?