PMI-ACP Preparation Exam Mocktest2 - Whizlabs

Question 6 of 120
Rami is an agile project manager with team of 9 working on a sprint, during the sprint one of the key stakeholders wants to add a new feature. Rami reviews the feature with PO and he agrees to add it in the product backlog. Remi’s concern is that he will not get any additional time and funding for this new feature. What should Rami do?