PMI-ACP Preparation Exam Mocktest2 - Whizlabs

Question 57 of 120
At the end of a sprint, the agile team was capable to deliver three user stories completely done as per definition with total estimated 24 story points and one incomplete user story with estimated at total 6 user story points but completed only 80%. Find the velocity of the team for this sprint.