PMI-ACP Preparation Exam Mocktest2 - Whizlabs

Question 52 of 120
You’re a software developer and a member of the team working on Agile projects. The team has just completed the third iteration and wants to measure the productivity in terms of velocity. Which of the following statement is not correct for the velocity?