PMI-ACP Preparation Exam Mocktest2 - Whizlabs

Question 41 of 120
An agile team is currently working on the third sprint of an agile project. The project stakeholders approached the scrum master to ask why a certain feature was removed from the sprint, how and where the money is being spent, and which features they have planned to be delivered in the next sprint. Which of the following is the best course of action for the scrum master to take in this situation?