PMI-ACP Preparation Exam Mocktest2 - Whizlabs

Question 34 of 120
An agile team is working on a software development project. The team has recently found a defect and the developers spent two days in fixing the defect while the started working on it from the next day when they found it. Then the deployment team spent the next day to deploy the correction at the customer premises. What does this four-day period represent?