Question 27 of 120
You are an agile practitioner and your eXtreme Programming (XP) team is working on a software development project. The team has been given the aggressive schedule deadline for the next product release. Due to this, the code produced is functional but the effort for the code development to add new features is taking longer duration. More instances of code coupling and unnecessary duplication were found in the code during the inspection. Which of the following would you recommend in the current situation as an agile practitioner?