PMI-ACP Preparation Exam Mocktest2 - Whizlabs

Question 107 of 120
The project stakeholders were not happy with the performance of the agile team as the team completed only 15 user stories out of the 20 planned in the recent iteration. The project stakeholders demanded answers and the team members told that they had to be involved in the routine task of supporting and maintaining prior releases due to which they missed the iteration goal. Should the routine task of supporting prior releases be there in the iteration?