PMI-ACP Preparation Exam Mocktest2 - Whizlabs

Question 101 of 120
An agile team involves multiple levels of project planning such that at the first level, they determine the project scope, resources, and schedule; also determine the user stories required to be developed in the release. At the next level, they coordinate with the product owner to prioritize the user stories according to their value to the customer. The next level involves daily planning. What does the agile team do in daily planning?