PMI-ACP Preparation Exam Mocktest1 - RITA

Question 86 of 120
You've been assigned the ScrumMaster of a team of engineers who used some Scrum practices on their last project but ran into problems. In hiring you, the sponsor mentioned that he didn't think they really knew what Scrum was. In your first meeting with your new team, they proudly explain that after they finish each piece of work, they update that step in their 20-page Scrum process document. How do you respond to this information?