Question 76 of 120
The business representative for your lean team hasn't been available for a few weeks due to a crisis in a foreign subsidiary. Fortunately the team has a good sense of the backlog priorities and has been able to continue making progress in her absence. However, there are now two work packages that haven't been approved yet--and at the end of this week there will be three. The team can keep going for a while, but the longer they have to wait for feedback and approval the more likely it is that they will get off track. What is this an example of?