PMI-ACP Preparation Exam Mocktest1 - RITA

Question 50 of 120
What is the process cycle efficiency of upgrading the computers for your distributed team, assuming that it takes your IT department 24 hours to get the computers from a vendor, 26 person hours of cumulative travel time, and 5 total person hours to actually do the upgrades?