PMI-ACP Preparation Exam Mocktest1 - RITA

Question 102 of 120
It is December 1st. Our next release is due June 1st, and we have 540 points left in our backlog. We are working in two-week iterations and want to use a control limit to monitor our velocity to make sure we stay on track to finish on time. What should our control limit be?