PMI-ACP Preparation Exam Mocktest3

Question 9 of 120
You are examining your project’s statistics. For the iterations one to six the team’s velocity has been 40, 50, 43, 47, 46, and 44 story points respectively. What is the most reasonable velocity estimate for the next sprint?