PMI-ACP Preparation Exam Mocktest3

Question 72 of 120
A team is developing an online appraisals management system using an incremental project life cycle. The customer is complaining about the number of bugs that are detected by the customer which should have been detected by the project team. Which of the following techniques encourage a mistake-proofing discipline?