PMI-ACP Preparation Exam Mocktest3

Question 7 of 120
An Agile team is working on a SCM project. At the end of the 3rd iteration, the team had successfully delivered 81 story points. The team was able to successfully address some improvement opportunities and during the 4th iteration the team was able to deliver 39 story points. What is the team’s current velocity?