PMI-ACP Preparation Exam Mocktest3

Question 53 of 120
A team estimates that the development of a feature will take four days and the testing of the feature will take two days. In order to account for the uncertainty, the team provides a six day estimate for the development and adds a 2-day lag to the testing activity. What did the team do?