PMI-ACP Preparation Exam Mocktest3

Question 36 of 120
An Agile team wishes to subcontract some of the project work. Rather than formalizing an entire contracting relationship in a single contract, the team wishes to describe different aspects of the relationship in different documents. Which of the following documents should be used to define the mostly fixed items such as warranties, arbitration, etc.?