PMI-ACP Preparation Exam Mocktest3

Question 35 of 120
Two projects are currently being analyzed. Project A will yield a net profit of $300,000 at the end of the second year. Project B will yield a net profit of $310,000 by the end of the fourth year. Assuming a 3% interest rate, which of the following is correct?