PMI-ACP Preparation Exam Mocktest3

Question 24 of 120
You are leading an Agile project. The team has proposed using a Kanban board to manage the team’s work in progress and spot bottlenecks. The following work flow has been agreed on for the Kanban board: Ready -> Develop and Unit Test -> Dev-Done -> System Test -> Done. According to this Kanban board, the response time of an item is the: