PMI-ACP Preparation Exam Mocktest3

Question 15 of 120
An Agile project’s product backlog contains 25 user stories estimated at 10 story points each. The team estimates that 60% of the effort will be required to develop the stories, while 40% of the effort will be required to test and deliver the stories. During the first iteration, the team was able to develop five stories but was only able to complete three of them. What was the team’s velocity?