PMI-ACP Preparation Exam Mocktest3

Question 107 of 120
Your organization has been awarded a contract to develop and implement a new resource management system for a client based in Asia. Your development team is distributed across Europe. You are also planned to relocate the implementation team to the client location. What would be your biggest challenge in such a setup?