PMI-ACP Preparation Exam Mocktest3

Question 10 of 120
You are managing a complex organizational redesign project. Reviewing project’s statistics you determined that the team completes 75 story points on average per iteration. Reviewing the backlog, you determine that there are about another 750 points remaining. If each interval is time-boxed at two weeks, when you do expect to complete the project?