A member of the Development Team takes the Scrum Master aside to express his concerns about data security issues. What should the Scrum Master do?
(choose the best answer)
Create a Product Backlog item for security.
Add security to the definition of "Done".
Ask the person to share the issue with the team as soon as possible.
Tell the Product Owner to stop further development of features until the issues are fixed.
Go check with the testers.