When is implementation of a Product Backlog item considered complete?
(choose the best answer)
When the item has no work remaining in order to be potentially released.
At the end of the Sprint.
When Quality Assurance reports that the item passes all acceptance criteria.
When all work in the Sprint Backlog related to the item is finished.