A Product Owner wants advice from the Scrum Master about estimating work in Scrum. Which of these is the guideline that a Scrum Master should give? these is the guideline that a Scrum Master should give?
(choose the best answer)
Estimates are made by the Development Team.
Estimates must be in relative units.
Estimates are made by the Product Owner, but are best checked with the Development Team.
Product Backlog items must be estimated in story points.
Scrum forbids estimating.