A Scrum Master is keeping a list of open impediments, but it is growing and they have been able to resolve only a small portion of the impediments. Which two techniques would be most helpful in this situation?
(choose the best two answers)
Discuss the impediments with the Development Team.
Add each open impediment to the Product Backlog.
Prioritize the list and work on them in order.
Arrange a triage meeting with all project managers.