During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog?
(choose the best answer)
When the Scrum Master has time to enter them.
As soon as possible after they are identified.
During the Daily Scrum after the Development Team approves them.
When the Product Owner identifies new work.