The Product Owner determines how many Product Backlog items the Development Team selects for a Sprint.
(choose the best answer)
True, accordingly to what was committed to the stakeholders.
False.
False, capacity and commitment are the Project manager's responsibility.
True.
False, the Scrum Master does that.
True, but only after confirmation by the resource manager that the Team has enough capacity.