It is mandatory for the Product Owner to monitor and share progress of the Product Backlog by using which method? (choose the best answer)
Any practice based on trends of work completed and upcoming work.
A Sprint Review acceptance report.
A Gantt chart.
A Value burn-up chart.
A Product or Release burn-down chart.