When should the Product Owner update the project plan?
(choose the best answer)
The Product Backlog is the plan in Scrum. It is updated as new information and insights emerge.
The Product Owner shouldn't be occupied by that. It is work for the Project Manager.
Before the Sprint Planning to know how much work will have to be done in the Sprint.
After the Daily Scrum to ensure an accurate daily overview of project progress.
Scrum forbids having a project plan.