When should the Product Owner update the project plan?
(choose the best answer)
Before the Sprint Planning to know how much work will have to be done in the Sprint.
Scrum forbids having a project plan.
The Product Owner shouldn't be occupied by that. It is work for the Project Manager.
After the Daily Scrum to ensure an accurate daily overview of project progress.
The Product Backlog is the plan in Scrum. It is updated as new information and insights emerge.