The "cone of uncertainty" can be used to do what?
(choose the best answer)
Determine the cost of a project before it is begun.
Project what will be completed by a given Sprint.
Determine whether to cut quality, similar to the "Iron Triangle" of project management.
Illustrate that, as a forecast lengthens, it is increasingly less certain.