As the Sprint Planning meeting progresses, the Development Team sees that the workload is greater than they can handle. Which two are valid actions? (choose the best two answers)
Cancel the Sprint.
Remove or change selected Product Backlog items.
Recruit additional Development Team members before the work can begin.
The Development Team ensures that the Product Owner is aware, starts the Sprint, and monitors progress.
The Development Team works overtime during this Sprint.