The Development Team finds out during the Sprint that they aren't likely to build everything they forecast. What would you expect a Product Owner to do?
(choose the best answer)
Re-work the selected Product Backlog items with the Development Team to meet the Sprint Goal.
Inform management that more resources are needed.
Cancel the Sprint.
Skip Product Backlog refinement activities.
Change the Sprint Goal.