Scrum is based on empirical process control theory. All of its artifacts must be transparent to ensure sufficient accuracy of inspection. Which two measures ensure that the Product Backlog is transparent?
(choose the best two answers)
The Product Backlog only has work for the next 2 Sprints.
The Product Backlog is managed using a web-based tool.
The Product Backlog is available to all stakeholders.
Each Product Backlog item has a MoSCoW priority.
The Product Backlog is ordered.