What activities would a Product Owner typically undertake in the phase between the end of the current Sprint and the start of the next Sprint?
(choose the best answer)
Update the project plan with stakeholders.
There are no such activities. The next Sprint starts immediately after the current Sprint.
Refine the Product Backlog.
Work with the Quality Assurance departments on the Increment of the current Sprint.