What typically happens if the Product Backlog is not sufficiently clear at Sprint Planning?
(choose the best answer)
Nothing in particular.
The meeting is cancelled so refinement can be done first.
It is compensated if the Product Owner gives the team a clear Sprint Goal instead.
The Scrum Master shouldn't allow this to happen. Look for a new Scrum Master and re-start the Sprint.
The Development Team has difficulties creating a forecast of work for the Sprint.