PSM II: Professional Scrum Master™ II (180 questions)

Question 6 of 180

At the end of the eighth Sprint, the internal sponsors are upset and angry with the progress of the product being built. The current state of the product is not as expected and will require additional Sprints and more budget than originally anticipated at the start of the project. What factors may have led to this? (Choose three.)