PSM II: Professional Scrum Master™ II (180 questions)

Question 114 of 180

During Sprint Planning, the Development Team was not able to confidently forecast a Sprint Backlog but the Scrum Team was able to create a Sprint Goal for upcoming Sprint. What action should the Scrum Master take?