A Scrum Master is keeping a list of open impediments, but it is growing and they have been able to resolve only a small portion of the impediments. Which two techniques would be most helpful in this situation?
(choose the best two answers)
Discuss the impediments with the Development Team.
Arrange a triage meeting with all project managers.
Add each open impediment to the Product Backlog.
Prioritize the list and work on them in order.