The Daily Scrum is an event that happens every day. What would be three key concerns if the frequency were to be lowered to every two or three days? frequency were to be lowered to every two or three days?
(choose the best three answers)
The Product Owner cannot accurately report progress to the stakeholders.
Too much work is spent updating the Scrum board before the meeting.
Opportunities to inspect and adapt the Sprint Backlog are lost.
The Scrum Master loses the ability to update the Gantt chart properly.
The Sprint plan may become inaccurate.
Impediments are raised and resolved more slowly.