What is the accountability of the Product Owner during Sprint 0?
(choose the best answer)
Make the complete project plan to commit date, budget and scope to the stakeholders.
Make sure enough Product Backlog items are refined to fill the first 3 Sprints.
There is no such thing as Sprint 0.
Determine the composition of the Development Teams so they have the capacity to deliver the completed forecast.
Gathering, eliciting, and analyzing the requirements that will be inserted into the Product Backlog.