Which statement best describes the Sprint Backlog as the output of the Sprint Planning?
(choose the best answer)
Each task is estimated in hours.
It is a complete list of all work to be done in a Sprint.
It is ordered by the Product Owner.
It is the Scrum Team's plan for the Sprint.
Every item has a designated owner.