Which statement best describes the Sprint Review?
(choose the best answer)
It is used to congratulate the Developers if they complete their forecast or to punish the Developers if they fail to meet their forecast.
It is a demo at the end of the Sprint for everyone in the organization to check on the work done.
It is when the Scrum Team and stakeholders inspect the outcome of a Sprint and figure out what to do next.
It is a mechanism to control the Developers activities during a Sprint.