A Project Manager working with your Scrum Team has raised concerns about progress and money spent. What are the two best responses?
(choose the best two answers)
Have a discussion with the Project Manager; share the current impediments and forecast for the Sprint.
Share the last stakeholder briefing document prepared by the Product Owner.
Promote transparency by sharing the Product Backlog and ensuring the Project Manager has access.
Scrum does not have Project Managers so disregard their concerns.
Show the Earned Value Analysis (EVA) report.