Why would you expect a Product Owner to care about the Scrum Team adhering to its Definition of Done?
(choose the best two answers)
To be able to punish the team when they do not meet their velocity goal for the Sprint.
The Definition of Done can affect the product’s total cost of ownership.
To forecast the team's productivity over time.
The Product Owner should not care about the Definition of Done, it is the Scrum Team's responsibility.
To have complete transparency into what has been done at the end of each Sprint.