Why would you expect a Product Owner to care about the Scrum Team adhering to its Definition of Done?
(choose the best two answers)
To forecast the team's productivity over time.
The Definition of Done can affect the product’s total cost of ownership.
To have complete transparency into what has been done at the end of each Sprint.
The Product Owner should not care about the Definition of Done, it is the Scrum Team's responsibility.
To be able to punish the team when they do not meet their velocity goal for the Sprint.