Project Management Professional (version 2023)

Question 80 of 200
A project manager received the project charter for a new product. The project is expected to have two main deliveries: the hardware part that has detailed specifications already defined, including a sample machine, and the user interface
software that has only a basic specification and a requirement for a user experience design approach.
Which project management approach should the project manager use?